APTOS
VILLAGE IMPROVEMENTS PHASE 2B
Project
Update 6/26/2020
APTOS VILLAGE BUSINESSES:
All Aptos village businesses are
open during construction operations.
Some may have modified operations and/or hours in accordance with
current health orders.
SCHEDULE UPDATE:
·
POTHOLING:
Potholing to determine exact locations of underground utilities is
expected to continue through Tuesday, June 30.
·
STORM DRAIN:
Storm drain installation is expected to begin after potholing is
completed and any utility conflicts have been addressed. Construction could begin as soon as July 1 and
will take about three weeks to complete.
·
CURB, GUTTER & SIDEWALK, North Side of
Soquel: Curb, gutter & sidewalk work
will begin after storm drain installation is complete and could begin as soon
as July 22. Construction will take about
three weeks to complete.
·
RAILROAD CROSSING: The railroad crossing schedule is still
being worked out. Construction may begin
in July.
The schedule is subject to change due to weather or other
conditions.
TRAFFIC CONTROL:
Traffic control consisting of one lane, two-way traffic with
flaggers will continue during construction operations. Delay times could be up to fifteen
minutes. For the safety of all, please use caution when moving through the
construction zone, obey all signage, and please share the road.
GENERAL:
The public’s
patience is appreciated during the construction process and we look forward to project
completion in November 2020. The
completion date is subject to change due to weather or other conditions.
Questions and
comments may be directed to:
Cristina Crocker, Resident Engineer, (831) 477-3956
Cristina.crocker@santacruzcounty.us