APTOS VILLAGE IMPROVEMENTS PHASE 2B

Project Update 6/11/2020

 

APTOS VILLAGE BUSINESSES:

All Aptos village businesses are open during construction operations.  Some may have modified operations and/or hours in accordance with current health orders.

SCHEDULE UPDATE:

·         POTHOLING:  Work on the Aptos Village Improvements Phase 2B project will begin on Tuesday, June 16 with potholing on Soquel Drive and Aptos Creek Road to determine exact locations of underground utilities.  Potholing work is expected to continue through Monday, June 22. 

·         STORM DRAIN:  Storm drain installation is expected to begin July 1 through July 21. 

·         RAILROAD CROSSING:  Railroad crossing work is expected to begin near the first of July.

TRAFFIC CONTROL:

Beginning Tuesday, June 16, traffic will be reduced to one lane, two-way traffic with flaggers at times.  Delay times could be up to fifteen minutes.  For the safety of all, please use caution when moving through the construction zone, obey all signage, and please share the road.

GENERAL:

The public’s patience is appreciated during the construction process and we look forward to project completion in November 2020.  The completion date is subject to change due to weather or other conditions.

Questions and comments may be directed to:
Cristina Crocker, Resident Engineer, (831) 477-3956