Tuesday – 7:00 AM start
Start grinding on Aptos St, move to Trout Gulch Rd, then Soquel
Dr. Patch pave may begin today.
Wednesday – Start time TBD, may be as early as 7 am (dependent on
temperatures).
Patch pave and first course paving if weather allows as forecast
updated with 80% chance of rain / thunderstorms.
* Please note that road surfaces will be rough until final
elevations are completed and there may be delays to the motoring public of up
to 20 minutes during operations. Each
day of work may continue to as late as 5 pm.