Paving Operations Schedule (Subject to change for actual conditions and weather permitting.)

Tuesday – 7:00 AM start
Start grinding on Aptos St, move to Trout Gulch Rd, then Soquel Dr.

Wednesday – Start time TBD, may be as early as 7 am (dependent on temperatures).
First paving course on Trout Gulch Rd then to Aptos St.
Second course on Trout Gulch Rd then to Aptos St.
Patch pave Soquel Dr north side.

Thursday – Start time TBD, may be as early as 7 am (dependent on temperatures).
First paving course on Soquel Dr and remaining initial course on Trout Gulch Rd if needed.
Finish paving Aptos Street.
Second course on Soquel Dr.

Friday – Start time TBD, may be as early as 7 am (dependent on temperatures).
Finish paving Trout Gulch Rd and Soquel Dr.