Friday, June 9, 2017

Project Update June 9, 2017

New curb, gutter, sidewalk and access ramp at the intersection of Trout Gulch Road and Aptos Street.


New sidewalk along Trout Gulch Road.

Concrete pouring of retaining curb for elevated sidewalk along Trout Gulch Crossing.


New driveway with access ramps at Trout Gulch Crossing.

There is temporarily no activity at the project site due to utility conflicts.  Materials are on order for adjustment of the Soquel Creek Water District water line.  Following adjustment, project construction will continue.  Water line work is anticipated to begin week of June 19, 2017.

Trout Gulch Crossing front and rear driveways accessing from Trout Gulch Road will remain closed for 28-day cure of concrete.


Monday, May 8, 2017

Project Update May 8, 2017

Project resumed from weather related delays on April 24, 2017.  Construction on new underground utilities continues.  Demolition and grading began for new sidewalk along Trout Gulch Road. 





Tuesday, April 18, 2017

Project Update April 18, 2017

Project continues on weather related delays as of last week.  Work resuming at end of week is dependent upon weather and site conditions.

Clearing and grubbing along Soquel Drive

Excavating for bus turnout

Installing safety shield at storm water quality manhole location on Aptos Street