Site Location

Site Location

Friday, June 9, 2017

Project Update June 9, 2017

New curb, gutter, sidewalk and access ramp at the intersection of Trout Gulch Road and Aptos Street.


New sidewalk along Trout Gulch Road.

Concrete pouring of retaining curb for elevated sidewalk along Trout Gulch Crossing.


New driveway with access ramps at Trout Gulch Crossing.

There is temporarily no activity at the project site due to utility conflicts.  Materials are on order for adjustment of the Soquel Creek Water District water line.  Following adjustment, project construction will continue.  Water line work is anticipated to begin week of June 19, 2017.

Trout Gulch Crossing front and rear driveways accessing from Trout Gulch Road will remain closed for 28-day cure of concrete.