APTOS
VILLAGE IMPROVEMENTS PHASE 2B
Project
Update 12/15/2020
APTOS VILLAGE BUSINESSES:
All Aptos village businesses are
open during construction operations.
Some may have modified operations and/or hours in accordance with
current health orders.
SCHEDULE UPDATE
·
STORM DRAIN:
Trenching for storm drain installation is complete. The tops of the drainage inlets remain to be
completed.
·
ELECTRIC AND FIBER OPTIC INFRASTRUCTURE: Much of this work has been completed,
including the installation of several pull boxes along Soquel Drive as well as
hanging of conduit on the bridge. Work
on the south side of Soquel Drive remains to be completed. This work is expected to be done by the end
of December.
·
TRAFFIC SIGNALS: Some of the signal poles have been installed
at Aptos Creek Road. Signals are
expected to be energized in January.
·
RAILROAD CROSSING: The new crossing has been installed and
Aptos Creek Road was reopened on 12/4/2020.
·
RAILROAD SIGNALS: Railroad signal work will continue through the
end of December.
·
CURB, GUTTER & SIDEWALK: Driveway reconstruction on Soquel Drive
adjacent to the bridge is taking place this week and expected to be complete by
mid-December. Curb, gutter &
sidewalk work north of the railroad tracks on Aptos Creek Road and on the south
side of Soquel Drive is expected to be completed by the end of December.
·
PAVING:
Paving will take place mid to late January.
·
RAISE UTILITIES: Utilities will be raised to final grade
following paving operations, in mid to late January.
·
STRIPING:
Striping will take place mid to late January.
The schedule is subject to change due to weather or other
conditions.
TRAFFIC CONTROL
Anderson
Pacific strives to keep two lanes of traffic open on Soquel Drive to the
greatest extent possible. At times, lane
closures with flaggers will be necessary.
Delay times could be up to fifteen minutes. For the safety of all, please use caution when moving through the
construction zone, obey all signage, and please share the road.
GENERAL
The Aptos Times published
a great Q & A article about this project in their July 15, 2020
edition. Please see link to the article
on the right.
The public’s
patience is appreciated during the construction process and we look forward to project
completion in January 2021. The
completion date is subject to change due to weather or other conditions.
Questions and
comments may be directed to:
Cristina Crocker, Resident Engineer, (831) 477-3956