Work is on break for Thanksgiving holiday following last week’s rain shutdown.

Work will resume on November 27, 2017 on the railroad crossing while switching to a night time schedule, 8 pm to 6 am.  One lane will remain open at all times with flaggers assisting motorists through the intersection during work hours for the safety of construction staff and the community.  A one night closure to lay down rail will need to be completed with more information forthcoming.  The detour route will be Valencia Road via Freedom Boulevard and Trout Gulch Road.

Progress on new bus shelter turnout: