Project Update April 18, 2017

Project continues on weather related delays as of last week.  Work resuming at end of week is dependent upon weather and site conditions.

Clearing and grubbing along Soquel Drive

Excavating for bus turnout

Installing safety shield at storm water quality manhole location on Aptos Street

Tuesday, March 28, 2017

The Aptos Village Improvement project has started!


The picture below shows the survey crew starting the Aptos Village Improvement Project.



Wednesday, March 22, 2017

Project Update


Week of March 20th Update:  Due to weather, the project is on rain delay and is not anticipated to begin this week.  Work will begin March 27, 2017, weather permitting.