Planned paving operations for this week completed a day ahead of schedule. Railroad utility work continues today.
This site provides information regarding the Aptos Village Improvements Phase 2B project.
Site Location
Friday, January 5, 2018
Thursday, January 4, 2018
Update January 4, 2018
First course paving completed
Wednesday. Final course paving in
progress including at Soquel Dr. / Trout Gulch Dr. intersection with long
traffic delays expected.
Tuesday, January 2, 2018
Subscribe to:
Posts (Atom)








