APTOS
VILLAGE IMPROVEMENTS PHASE 2B
Project
Update 8/6/2020
APTOS VILLAGE BUSINESSES:
All Aptos village businesses are
open during construction operations.
Some may have modified operations and/or hours in accordance with
current health orders.
SCHEDULE UPDATE
·
STORM DRAIN:
Storm drain revisions due to utility conflicts have been
completed. Installation is expected to
begin soon, likely this month, and will take about four weeks to complete.
·
CURB, GUTTER & SIDEWALK, North Side of
Soquel: Curb, gutter & sidewalk work
will continue on the north side of Soquel Dr. with curb and gutter being poured
this week and sidewalk soon to follow.
·
RAILROAD CROSSING: The railroad crossing schedule is still
being finalized and will be released when it becomes available.
The schedule is subject to change due to weather or other
conditions.
TRAFFIC CONTROL
So far, the contractor’s operation has allowed two lanes of
traffic to remain open much of the time.
Traffic control consisting of one lane, two-way traffic with flaggers will
be required during upcoming construction phases. Delay times could be up to fifteen
minutes. For the safety of all, please use caution when moving through the
construction zone, obey all signage, and please share the road.
GENERAL
The Aptos Times
published a great Q & A article about this project in their July 15, 2020
edition. Please see link to the article
on the right.
The public’s
patience is appreciated during the construction process and we look forward to project
completion in November 2020. The
completion date is subject to change due to weather or other conditions.
Questions and
comments may be directed to:
Cristina Crocker, Resident Engineer, (831) 477-3956