Wednesday, September 27, 2017
Update September 27, 2017
Work in Aptos on Monday and Tuesday was for the
Soquel Creek Water District rerouting a water line running along Soquel
Drive. Today thru Friday they will be working on the storm drain crossing
Soquel Drive. Expect shoulder closure and/or lane closures under traffic
control on Soquel Drive just east of Trout Gulch Road.
Tuesday, September 19, 2017
Project Update September 19, 2017
Electrical
and traffic signal work continues on Soquel Drive this week.
For
safety of construction team and the community, on Tuesday, there is a lane
shift for Soquel Drive southbound lane. On Wednesday, there will be a
lane shift on both Soquel Drive southbound and northbound lanes. No
closures are planned.
Wednesday, September 13, 2017
Project Update September 13, 2017
Work
continues in the area between Soquel Drive and Aptos Street through Friday.
On Friday, there will also be work adjacent to the Soquel Drive and Trout
Gulch Road intersection.
For the
safety of the construction team and the community, there will be lane shifts on
Soquel Drive beginning noon on Wednesday, 9/13/17, through Thursday, 9/14/17.
There will also be a lane shift on Trout Gulch Road onto Soquel Drive on
Friday, 9/15/17. No lane closures are planned.
Thursday, September 7, 2017
Project Update September 9, 2017
Removal of railroad arm equipment
at the intersection of Trout Gulch Road and Soquel Drive.