Site Location

Site Location

Wednesday, September 13, 2017

Project Update September 13, 2017


Work continues in the area between Soquel Drive and Aptos Street through Friday.  On Friday, there will also be work adjacent to the Soquel Drive and Trout Gulch Road intersection.  

For the safety of the construction team and the community, there will be lane shifts on Soquel Drive beginning noon on Wednesday, 9/13/17, through Thursday, 9/14/17.  There will also be a lane shift on Trout Gulch Road onto Soquel Drive on Friday, 9/15/17.  No lane closures are planned. 

Thursday, September 7, 2017

Project Update September 9, 2017


Removal of railroad arm equipment at the intersection of Trout Gulch Road and Soquel Drive.

 
 
Removal of railroad track.


Thursday, August 31, 2017

Project Update August 31, 2017


Work at project site will resume Wednesday, September 6, 2017, on railroad signals and track in areas outside of Soquel Drive and Trout Gulch Road intersection.  For safety of construction team and the community, there will be a lane shift on Trout Gulch Road onto Soquel Drive.  No lane closures are planned.