Site Location

Site Location

Friday, March 30, 2018

Update March 30, 2018


Paving operations continue today on Trout Gulch Road.  Please note that road surfaces will be rough until final elevations are completed and there may be delays to the motoring public of up to 20 minutes during operations. 

 
 

Friday, January 5, 2018

Update January 5, 2018

Planned paving operations for this week completed a day ahead of schedule.  Railroad utility work continues today.





Thursday, January 4, 2018

Update January 4, 2018


First course paving completed Wednesday.  Final course paving in progress including at Soquel Dr. / Trout Gulch Dr. intersection with long traffic delays expected.

* Please note that road surfaces will be rough until final elevations are completed.  Each day of work may continue to as late as 5 pm.

 

Tuesday, January 2, 2018

Update January 2, 2018

Grinding in progress:





Update January 2, 2018

Paving Operations Schedule (Subject to change for actual conditions and weather permitting.)

Tuesday – 7:00 AM start
Start grinding on Aptos St, move to Trout Gulch Rd, then Soquel Dr.  Patch pave may begin today.

Wednesday – Start time TBD, may be as early as 7 am (dependent on temperatures).
Patch pave and first course paving if weather allows as forecast updated with 80% chance of rain / thunderstorms.

* Please note that road surfaces will be rough until final elevations are completed and there may be delays to the motoring public of up to 20 minutes during operations. Each day of work may continue to as late as 5 pm. 

Friday, December 29, 2017

Update December 29, 2017


Paving Operations Schedule (Subject to change for actual conditions and weather permitting.)

Tuesday – 7:00 AM start
Start grinding on Aptos St, move to Trout Gulch Rd, then Soquel Dr.

Wednesday – Start time TBD, may be as early as 7 am (dependent on temperatures).
First paving course on Trout Gulch Rd then to Aptos St.
Second course on Trout Gulch Rd then to Aptos St.
Patch pave Soquel Dr north side.

Thursday – Start time TBD, may be as early as 7 am (dependent on temperatures).
First paving course on Soquel Dr and remaining initial course on Trout Gulch Rd if needed.
Finish paving Aptos Street.
Second course on Soquel Dr.

Friday – Start time TBD, may be as early as 7 am (dependent on temperatures).
Finish paving Trout Gulch Rd and Soquel Dr.

* Please note that road surfaces will be rough until final elevations are completed and there may be delays to the motoring public of up to 20 minutes during operations.  Each day of work may continue to as late as 5 pm.