This site provides information regarding the Aptos Village Improvements Phase 2B project.
Site Location

Wednesday, November 29, 2017
Sunday, November 26, 2017
Monday, November 20, 2017
Project Update November 20, 2017
Work is on break for Thanksgiving
holiday following last week’s rain shutdown.
Work will resume on November 27, 2017 on
the railroad crossing while switching to a night time schedule, 8 pm to 6
am. One lane will remain open at all
times with flaggers assisting motorists through the intersection during work
hours for the safety of construction staff and the community. A one night closure to lay down rail will
need to be completed with more information forthcoming. The detour route will be Valencia Road via
Freedom Boulevard and Trout Gulch Road.
Progress on new bus shelter turnout: