Lane shifts on Soquel Drive is expected
for the safety of construction staff and the community.
This site provides information regarding the Aptos Village Improvements Phase 2B project.
Site Location

Thursday, October 19, 2017
Project Update October 19, 2017
Work continued this week on the storm
drain system. Work through the end of
the week will be in the new bus stop area.
Thursday, October 12, 2017
Update October 12, 2017
Continuing
storm drain utility work on Thursday and Friday. For safety of public and
construction crew, the right turn lane on Trout Gulch Road will be
closed. There will also be intermittent flagging in Trout Gulch Road and
Soquel Drive intersection.
Wednesday, October 11, 2017
Project Update October 11, 2017
Work
today in the project vicinity is specifically on the Soquel Creek Water
District water line only. A short lane
closure in the southbound lane of Soquel Drive is expected for the District’s
water line work.
Thursday, October 5, 2017
Project Update October 5, 2017
Storm drain line work continues through
Friday on Trout Gulch Road. Lane shifts
and intermittent one lane, 2-way traffic is expected for the safety of
construction staff and the community.
Wiring for traffic signal poles also
continues this week.
Tuesday, October 3, 2017
Project Update October 3, 2017
Tuesday, temporary plates on Soquel
Drive to be removed and temporary patching to be placed. Brief lane closure expected.
Storm drain line work continues Tuesday
and Wednesday in Trout Gulch Drive. One
lane, 2-way traffic is expected for the safety of construction staff and the
community.
Traffic signal poles installed week of
September 18th will not be energized until electrical and associated
signal work is complete.
Subscribe to: