Preparation work for utility
relocation and various project tasks is anticipated week of June 26, 2017.
This site provides information regarding the Aptos Village Improvements Phase 2B project.
Site Location

Wednesday, June 21, 2017
Friday, June 9, 2017
Project Update June 9, 2017
New curb, gutter, sidewalk and access ramp at the intersection of Trout Gulch Road and Aptos Street.
New sidewalk along Trout Gulch Road.
Concrete pouring of retaining curb for elevated sidewalk along Trout Gulch Crossing.
New driveway with access ramps at Trout Gulch Crossing.
There is temporarily no activity at the project site due to utility conflicts. Materials are on order for adjustment of the Soquel Creek Water District water line. Following adjustment, project construction will continue. Water line work is anticipated to begin week of June 19, 2017.
Trout Gulch Crossing front and rear driveways accessing from Trout Gulch Road will remain closed for 28-day cure of concrete.
Subscribe to:
Posts (Atom)